Question: An activity may consume more time than its estimated time, or start later than its earliest possible start time without affecting the total duration of a project when?
If the activity is not on the critical path, then it can consume more time or start later without affecting the total duration of a project. An activity that is not on the critical path is considered to be a non-critical activity and its start and finish times can be adjusted without a significant impact on the project duration.